Once free slide the drip edge out and discard.
Installing new roof drip edge.
Slip the wide flat flange of the material all the way under the first course of roof shingles as illustrated.
The drip edge is nailed in place using 1 1 2 galvanized roofing nails.
Use a flat pry bar and hammer to pry the nails out of the drip edge gently.
While the vertical leg should be placed 1 4 1 2 away from the fascia.
Install roof drip edge along the eaves add underlayment then place drip edge along the gable end.
Using drip edge with a nailing edge approx.
If it doesn t pull the drip edge out slightly from under the shingles.
Gently lift up the shingles on the edge of the roof and locate the nails holding the existing drip edge onto the roof.
On the rakes the drip edge goes over the membrane so the roofers apply the membrane first.
Make sure the outer edge extends over the gutter.
Place a nail at one end then the other.
You ll need to ask another roofing professional to hold up the shingles while you do so.
Make sure the corner is tight and that the bottom edge is tight to the fascia before nailing off the drip edge.
Secure the drip edge with roofing cement.
Install the new drip edge as described above with cement and nails.
To install a drip edge on a newly constructed roof or on a re roofing job attach the drip edge along the roof s eaves first.
On the eaves the peel and stick goes over the drip edge though there is some argument in the industry as whether this is the best way to install drip edge.
The common practice of installing drip edge tightly to the fascia creates a path for water to cling to the fascia and run down it wearing the face of the fascia and shortening its lifespan.
You may need to nail through the starter strip into the drip edge.
4 deep nail the drip edge to the sheathing every 16.
How to install a drip edge.
The roof leg should extend a minimum of 2 back onto the roof sheathing.